Boiler plant No. 2, Logoysk municipal utility

Completed 4 MW woody-biomass boiler plant in Pleshchenitsy using HAMECH equipment.

Boiler plant No. 2, Logoysk municipal utility
Output / batch
4 000 кВт
Equipment
KWH-2000×2
AZSD-1000×4
Year
2007–2009
Location
Плещеницы

The new boiler plant No. 2 in Pleshchenitsy was built for local woody fuels: chips and sawdust.

The documented equipment package includes two KWH-2000 boilers and four AZSD-1000 combustion systems. The plant was commissioned in 2009.

References · 2010

РУП «Логойский комхоз»

Operating reference for 2 MW and 4 MW KWH/AZSD systems.